The Lagos State Government says it will commence repair work on the failed portions of the Lagos-Badagry Expressway on Monday, March 29, 2021.
The repairs, which will last for eight weeks, will be completed on May 31, 2021, according to a statement by the state Ministry of Transportation.
The statement was signed and released by the Lagos State Commissioner for Transportation, Dr Frederic Oladeinde, on Saturday, March 27, 2021.
He identified the affected portions to include Maza-Maza, Signal Barracks and Mile 2, adding that a traffic diversion plan had been worked out with adequate traffic management measures in place to ease movement and minimise the expected inconveniences.
The commissioner advised motorists heading towards Apapa from Maza-Maza to use the newly constructed slip road by the Total Filling station to connect the ramp and access Apapa.
Oladeinde in his statement said, “The repairs will last for eight weeks, commencing from Monday, May 29. The job will be completed on May 31.
“Traffic heading to Orile/Suru from Maza-Maza will be diverted to the opening at Total Filling Station to link Toll lane and continue the movement to Orile. Such motorists could also go through the opening at Signal Barracks to access the service lane from toll lane, to continue their journey.
“Motorists going to Oshodi from Maza-Maza are also advised to use the opening at Total filling station to connect toll lane and drive down to the opening after Mile 2 underpass to utilise the opening before Signal Barracks and access the ramp with counter flow to Apapa-Oworonshoki Expressway to continue their journey to Oshodi.
“Those coming from Oshodi to Orile will be directed to Mile 2, Oke to connect the ramp to Signal Barracks and continue their journey to Orile, while those going back to Oshodi should make a U-turn and continue their trip to Oshodi.
“Other motorists coming from Otto Wharf should use the opening before Signal Barracks and connect the toll lane and continue their journey to Alaba/Orile,” he said.
The commissioner warned the general public against the assault of Lagos State Traffic Management Authority officials who would be deployed to manage traffic on that axis as anyone caught in such an act will be decisively dealt with.
The reconstruction of the Lagos-Badagry expressway, which began in 2010, involves the widening of the road from 4 lanes to 10 lanes for vehicles, and a new mass transit line that will operate in the median.
The project, which has faced a series of delays, also includes a light rail project with train stations.
About a month ago, the Lagos State Government set up a seven-member ad hoc committee to be headed by the Deputy Governor of the state, Dr Obafemi Hamzat, with a mandate to have a dialogue with the Federal Government and secure a guarantee for quick completion of ongoing work on the Okokomaiko-Seme border stretch of the Lagos-Badagry Expressway.
Osun man on death row for fowl theft shares how police subjected 17-year-old self to…
Oil cabal sponsoring blackmails against Tompolo, Otuaro, Kyari, say Ijaw youths Stakeholders under the Ijaw…
NURTW scribe felicitates Nigerians on Xmas, urges caution The General Secretary of the National…
Why we displayed 'Jesus Christ is not God' banner at Lekki mosque -Imam …
CBN fines bank found hoarding cash N150m The Central Bank of Nigeria (CBN) has imposed…
Lagos-Calabar coastal road: Train track work begins 2025, says minister The Federal Government plans to…