Lagos State Governor Babajide Sanwo-Olu says his administration will complete the construction of the Lagos Rail Mass Transit (LRMT), Red Line Project, before the end of his first term in office.
He said the line would have five overpasses to replace all level crossings along the route and avert train/vehicle collision.
Sanwo-Olu stated this on Tuesday after the inspection tour of the project that took him to Yaba and Ebute Meta axis of the state, where train stations and vehicular bridges overpass are sited.
He said the train stations were 75 to 80 per cent completed and while overpass was 95 per cent completed.
He said the state government was working with all the stakeholders, most especially the Nigerian Railway Corporation (NRC) to complete the project.
Five overpasses
He said the project at different stages of completion would have five overpasses, to be located at Oyingbo, Yaba, Mushin to Onipanu, and Ikeja, to forestall train-vehicle accidents and reduce travel time for Lagosians.
The governor said the state government was particularly discussing with the NRC in the area of train signalling, adding that there was a need to “harmonize the signalization between our rail infrastructure and the Nigerian Railway Corporation rail infrastructure.”
He also said, “All the vehicular overpass bridges are very important because of the unfortunate train and bus accident that we saw a few weeks ago at Shogunle.”
Sanwo-Olu said the two train stations on the axis were at various advance stages of completion and expressed satisfaction with the level of work on the Redline rail project and on the stretch of Ebute-Meta to Agbado.
The governor said when the project is completed, the unfortunate train accident which claimed lives at the PWD rail crossing could be averted considering the design of the ongoing modern red line project.
He said, “You have seen the train stations, especially the Yaba and Oyingbo train stations. We started at Yaba and we also have a vehicular bridge overpass. With the train station we believe we are about 75 to 80 per cent complete and with the bridge it’s about 90 to 95 per cent but the adjoining road to Yaba would be cleaned up.”
2027: Atiku, Obi, Makinde absent as opposition parties chart path to common candidate The presidential…
Security Forces Rescue 10 NYSC Members from Kogi Forest Joint Police, Military, and DSS Operation…
Messi Retires from Argentina National Team for Second Time at 39 Football legend announces emotional…
IPOB Gives FG 14-Day Ultimatum to List Nnamdi Kanu's Appeal or Face Election Boycott Separatist…
Tinubu’s FBI records: Reno Omokri explains why President opposes release Former presidential aide Reno Omokri…
Seyi Tinubu Can Change Things at NFF — Obafemi Martins Backs President's Son for Football…