CCECC to complete Lagos-Ibadan rail signals, communication system March 2022

Published

on

Three months after the inauguration of the standard gauge Lagos-Ibadan rail by President Muhammadu Buhari, the signal and communication system has not been operational.

The Project Liaison Officer of China Civil Engineering Construction Corporation (CCECC), Mr Yakubu Adogie, who stated this, however, promised that the company was already working to complete the system before the first quarter of 2022.

He spoke in Lagos when members of the National Assembly Joint Committee on Transportation visited the Ebute Meta headquarters of the Nigerian Railway Corporation and inspected the new rail line including the Bola Tinubu Railway Station, Apapa.

Concerns have been raised about system along new railway corridor over delay in the completion of the signalling system.

The signalling system helps to maintain a safe distance between trains on the same track, safeguard train movement at junctions and regulate their passage according to the service density and speed required.

A statement by the NRC on Monday reported the CCECC liaison officer as saying that the company was also working on the plumbing, power supply and telecommunications of other stations within the new Lagos-Ibadan railway corridor.

Adogie lamented that despite intervention of the Minister of Transportation, Mr Rotimi Amaechi, in July and payment of compensation, the Nigeria Customs Service (NCS) log room building had not been demolished to give way for the construction of the other two lines to connect Apapa port.

The Projects Manager of TEAM Construction Company Nig. Ltd, Leonardo Portanova, spoke on the overhead bridges and crossings in the Lagos end of the rail line.

According to him, the Lagos State Government is constructing seven overhead bridges while TEAM would build six overhead crossings.

The Chairman, Joint Senate/House Committee on Transportation, Abdulfatai Buhari, said the legislators would support the NRC with necessary legislative framework to ensure effective rail transport and boost inter-regional business in the country.

He promised the committee’s commitment for excellent delivery on the NRC’s mandate in line with international best practices.

“You are all aware that the joint committee is carrying out its statutory constitutional responsibilities to ascertain the level of work done.

He said, “We are here to oversee how funds appropriated in the past fiscal years were expended and how much needed for the smooth running of the corporation against the next budgetary allocation.

“We had the benefit of listening to your presentation and recommendations at the last budget defence as regards the performance on 2020 budget and 2021 budget appropriations.”

Buhari said that the committee’s visit was not to witch-hunt the corporation but to collaborate and ensure the rail revitalisation agenda as well as infrastructural development programme of the current administration.

The Chairman, House of Representatives Committee on Transportation, Hon. Abbas Tajudeen, asked the contractors to open a good channel of communication with them to enable that the committee defend them on their requirements to make the land transport viable for business.

He also urged the NRC management to always make their reports available quarterly to improve the synergy with the National Assembly.

He said the committee also sought the need for housing scheme for workers to improve staff welfare and enhance efficiency.

Earlier in his presentation, the NRC Managing Director, Mr Fidet Okhiria, gave current personnel strength of the corporation as 10,672 with current personnel cost of N9.137 billion for 2021.

He also said that a total of 1,000 additional workers would be required for the operation of the new Lagos-Ibadan rail line, with additional wage bill of N567, 451,300 per annum.

He pleaded with the committee to support the NRC to achieve its goal of expanding the operations nationwide for effective transportation of people and freight.

Okhiria added, “On corporation’s revenue generation since 2020, NRC has remitted N1. 126bn to Federal Government approved dedication TSA Account domiciled with the CBN.”

 

Railway

Finally, Port Harcourt-Aba train service begins with four-day free ride

Published

on

Finally, Port Harcourt-Aba train service begins with four-day free ride

A four-day free train ride from Port Harcourt in Rivers State to Aba, Abia State will begin today, May 1, signifying commencement of rail service along the 62-kilometre route.
This is coming a month after the train operation on the rehabilitated narrow gauge track was initially meant to start.
Minister of Transportation, Senator Saidu Alkali, inaugurated the rail service in Port Harcourt on Tuesday.

Alkali said the project was part of the rehabilitation of 1,443km Port Harcourt to Maiduguri narrow gauge rail line.

He said that the Port Harcourt to Aba section of the project was the initial part of the Eastern narrow-gauge railway, aiming to connect five geopolitical zones of the country.

He said, “The Federal Government is pleased to inaugurate the train service from Port Harcourt to Aba, a key priority area of President Bola Tinubu’s administration.
“We are grateful to God for the completion of the Port Harcourt to Aba section, which will bring succour to the people.
“The Eastern narrow gauge covers five geo-political zones of the country, including South-South, South-East, North-Central, North- West, and North-East,” he said.
Aba to Enugu rail is next
Alkali said following the completion of the first segment and the start of commercial operations of the rail service, the Federal Government would soon commence the construction of the Aba to Enugu rail project, linking the two states together.
He added that his ministry was working with investors to ensure the conversion of the locomotive across the country from diesel to Compressed Natural Gas (CNG) to reduce transportation costs further.
“Shortly, we will take a train ride from Port Harcourt to Aba, which means that from today, passenger train service has commenced.
“We will continue the project from Aba to Enugu and from Port Harcourt to both Onne and Port Harcourt seaports for freight services.
“The ministry is currently in discussion with an investor to convert our locomotive from diesel to Compressed Natural Gas (CNG) to reduce transportation costs further,” he said.
The minister assured Nigerians that arrangements were being made with security agencies to ensure adequate security along the rail routes.
He also announced free train rides from Port Harcourt to Aba between May 1 to May 4.
“The train will depart from Port Harcourt to Aba at 8am daily, while it will leave Aba to Port Harcourt at 3pm daily.
“Full commercial operations will resume on May 7, 2024,” he said.

Continue Reading

Railway

Our medical team tried to rescue policeman who died on Abuja-Kaduna train – NRC 

Published

on

Our medical team tried to rescue policeman who died on Abuja-Kaduna train – NRC 

 

The Nigerian Railway Corporation has reacted to the death of policemen while on escort duty aboard the Abuja-Kaduna train on April 5, saying the deceased received medical attention on the train.

It said this in a statement on Tuesday.

The police escort attached to the train was said to have died on the train conveying passengers from Kaduna to Abuja last Thursday.

The police officer reportedly complained of chest pain before he collapsed and died.

Some have accused the NRC of not having medical personnel on board.

But the NRC said there was a medical doctor on duty on the train when the incident happened.

It disclosed that the official was also assisted by a passenger, also a medical practitioner.

The statement read in part, “The NRC management wishes to emphatically inform the general public that we have well trained medical personnel and equipped medical cubicle to attend to any emergency health challenges of our esteemed passengers.

“For the avoidance of doubt, the medical personnel on duty was Mariam Abdulai who was assisted by a good Samaritan medical practitioner that happens to be our passenger on board to revive the ailing cop but was in futility.

“The management of the NRC expresses its heartfelt condolence to the bereaved family of the late police inspector, Nambut Selbol, who was escort on duty in Abuja – Kaduna train service on that fateful day.”

Continue Reading

Railway

Abuja metro rail 97% ready, says Wike after 30-minute ride

Published

on

Wike in 30-min ride on Abuja metro train, says it’s 97% ready

Minister of the Federal Capital Territory (FCT), Nyesom Wike, on Friday undertook a 30-minute ride on the Abuja metro train after an inspection of the intra-city rail project.

The train ride was done after an inspection tour from the Metro Station in Central Area to the Nnamdi Azikiwe International Airport, Abuja.

He disclosed that the Rail Mass Transit (ART) project was 97 per cent ready.

Wike President Bola Tinubu would be happy to commission the Abuja Rail Mass Transit project in May.

The minister described the development as a “dream comes true”.

He said the project would be ready for inauguration to celebrate Tinubu’s one year in office.

Wike said Tinubu had approved the schedule for the inauguration of projects in the FCT.

The minister said, “We are very happy. We are almost 97 per cent completed. All works are ongoing to make sure that the May delivery date is a reality.

“I believe this is one of the projects Mr President would like to inaugurate, because it is very key to the development of the economy.

“For me, it is a dream come true, and we are happy that after all said and done, the metro line will be put to use for Nigerians, come May 29″.

After the test ride from the Metro Station to the Airport, the minister declared that it would be more convenient to use the train than vehicles to go to the airport.

He added, “I am really impressed with the contractor, China Civil Engineering Construction Corporation (CCECC).

“The company has assured us that all the renovation works on the stations will be ready before the commissioning date.”